SHARAVATI RESIDENCYMahaRERA P52800009750
PLOT NO 5 SURVEY NO 85 , HISSA NO 2/1, Jalgaon, 415712
Jan 2022
Possession
63.6%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jan 2022) has passed with construction at 63.6%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2022 per the RERA filing.
Official RERA facts
- Registration
- P52800009750
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- January 2022originally January 2021
- Construction
- 63.6% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply20%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingdone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 6
Buyer community
Connect with other buyers and owners of SHARAVATI RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHARAVATI RESIDENCY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.