PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

MADHUMALTI PRESTIGEMahaRERA P52800010287

by VIKAS DEVLEKAR

CTS NO 219, 220, 221, 222, 223, 224, 225, 226, 227, 227/1, S.NO.-92/1, S.NO.-75, Natraj naka, 415712

Dec 2021
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 90.9%.

Official RERA facts

Registration
P52800010287
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
SOCIETY ROOMdone

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of MADHUMALTI PRESTIGE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MADHUMALTI PRESTIGE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.