Under construction
Nisarga ResidencyMahaRERA P52800014956
by Namoh Nature Group Builders & Developers
Survey No. 36A, Hissa No. 20/20 and 21/21, Kherdi, 415604
Dec 2026
Possession
76.6%
Built
6
Complaints
0
Units
High risk
- Possession delayed ~5 yrs. Originally promised Jun 2022, now proposed Dec 2026 per the RERA filing.
- 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52800014956
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally June 2022
- Construction
- 76.6% complete
- Units sold
- 0 of 0
RERA complaint record6 records
- ComplaintCC125031507 Sept 2025Vilas Nathu Bagul vs Namoh Nature Group Builders & Developers
- ComplaintCC125031527 Sept 2025Anil Nathu Bagul vs Namoh Nature Group Builders & Developers
- ComplaintCC125031537 Sept 2025sudhanshu dwarkanath vanage vs Namoh Nature Group Builders & Developers
- ComplaintCC00600000025172713 Sept 2022Viddesh Shinde vs Pravin ShindeOrder of Viddesh Shinde (1).pdf on MahaRERA
- ComplaintCC00600000019700313 May 2021Viddesh Vijay Shinde vs Pravin ShindeCC006_197003.pdf on MahaRERA
- Misc. applicationCC00600000019700313 May 2021Viddesh Vijay Shinde vs Pravin ShindeCC006_197003.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Jan 2018
- Floors
- 6
Buyer community
Connect with other buyers and owners of Nisarga Residency โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Nisarga Residency. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.