PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SARVADA HEIGHTSMahaRERA P52800015906

by SARVADA ENTERPRISES

62731450B2,1450B3,1450B1,1450A3, DHAWANEWADI, 416701

Sept 2025
Possession
90.8%
Built
0
Complaints
51
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Sept 2022, now proposed Sept 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 90.8%.

Official RERA facts

Registration
P52800015906
Status
New
Stage
Certificate Signed
Possession
September 2025originally September 2022
Construction
90.8% complete
Units sold
17 of 51

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Apr 2018
Floors
6
Unit mix
39 res ยท 12 comm

Buyer community

Connect with other buyers and owners of SARVADA HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SARVADA HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.