PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

NARMADAA NIWAASMahaRERA P52800015946

by MAHENDRA SHANTARAM KADAM

37A1A11, RAJAPUR, 416702

Dec 2026
Possession
81.6%
Built
0
Complaints
51
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52800015946
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2021
Construction
81.6% complete
Units sold
34 of 51

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingdone
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingdone

Building & registration

RERA registered
Apr 2018
Floors
6
Unit mix
46 res ยท 5 comm
Architect
Shirish Ghorpade

Buyer community

Connect with other buyers and owners of NARMADAA NIWAAS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NARMADAA NIWAAS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.