SAIDHAM PUSHYAMahaRERA P52800019793

by B.G.SOVANI AND ASSOCIATES

7178/A1/2, PAGZARI, 415605

Mar 2024
Possession
32.7%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 32.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2024 per the RERA filing.

Official RERA facts

Registration
P52800019793
Status
New
Stage
Certificate Signed
Possession
March 2024
Construction
32.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2019
Floors
4

Buyer community

Connect with other buyers and owners of SAIDHAM PUSHYA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAIDHAM PUSHYA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.