SWAPNASRUSHTI BLDG-2MahaRERA P52800019873

by SWAPNAPURTEE REALTY PVT LTD

S NO. 103 HNO.3 7 12 SNO 104 H NO 6, 7, 8 32, RADHAKRISHNA NAGAR, 415605

Mar 2027
Possession
63.6%
Built
0
Complaints
50
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Mar 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P52800019873
Status
New
Stage
Certificate Signed
Possession
March 2027originally December 2024
Construction
63.6% complete
Units sold
44 of 50

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingdone
Energy managemcntdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Mar 2019
Floors
6
Unit mix
50 res ยท 0 comm
Architect
Nagsen Kamble

Buyer community

Connect with other buyers and owners of SWAPNASRUSHTI BLDG-2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SWAPNASRUSHTI BLDG-2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.