Horizon View ExoticMahaRERA P52800019936

by Nasir Abdul Rehaman Khot

S No 28 H No 23 S No 29 H No 5, Mirjoli, 415605

Dec 2030
Possession
43.2%
Built
0
Complaints
250
Units
High risk
  • Possession delayed ~6 yrs. Originally promised May 2025, now proposed Dec 2030 per the RERA filing.

Official RERA facts

Registration
P52800019936
Status
New
Stage
Certificate Signed
Possession
December 2030originally May 2025
Construction
43.2% complete
Units sold
37 of 250

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsdone
Street Lightingnot started
Community Buildingsnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2019
Floors
11
Unit mix
201 res ยท 49 comm
Architect
SAJID ABDUL MAJID ALWARE

Buyer community

Connect with other buyers and owners of Horizon View Exotic โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Horizon View Exotic. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.