Under construction

Balajis Skye Chalet-16MahaRERA P52800020592

by Sree Balaji Constructiions

S No 251A1 H No 1112 CTS No 2935B11 S No 251A1 H No 1116 CTS No 2935B17, Ratnagiri, 415612

Dec 2024
Possession
78.2%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 78.2%.

Official RERA facts

Registration
P52800020592
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
78.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2019
Floors
9

Buyer community

Connect with other buyers and owners of Balajis Skye Chalet-16 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Balajis Skye Chalet-16. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.