MARIGOLDMahaRERA P52800022149
Gat No 3546A Part, Gat No 3547A , Gat No 3547B , S No 948, 949 and 102 Part, Lanja, 416701
Dec 2026
Possession
90.9%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52800022149
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2021
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC0060000001933661 Jul 2020Prabhakar Mahadev Dorle and Prasad Prabhakar Dorle vs Sameer Mahamad GhareORDER-193366.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Electrical meter room, sub-station, receiving stationdone
Building & registration
- RERA registered
- Sept 2019
- Floors
- 5
Buyer community
Connect with other buyers and owners of MARIGOLD โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MARIGOLD. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.