Possession
40.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Apr 2025) has passed with construction at 40.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2025 per the RERA filing.

Official RERA facts

Registration
P52800034058
Status
New
Stage
Certificate Signed
Possession
April 2025
Construction
40.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

Manda Padurang Mayekar

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Mar 2022
Floors
9
Plot / CTS / survey no.
204
Planning authority
Others
Approved layout land
1,180.3 sq.m
Land for this registration
1,180.3 sq.m
Recreational open space
1,180.3 sq.m
Permissible built-up area
1,551.62 sq.m
Registered office
OM ENCLAVE
Plot boundaries
North
CTSNO65
South
CTSNO56
East
CTSNO62
West
18MT WIDE MUNCIPAL ROAD
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • STATE BANK OF INDIA โ€” 112555
    IFSC SBIN0000467
    KHAREGHAT ROAD OPP GEETA BHAVAN RATNAGIRI

Commencement Certificate documents

  • Commence Certificate.pdf
  • doc12854620230109163058_11zon.pdf

Buyer community

Connect with other buyers and owners of SAMRUDDHI DEVELOPERS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAMRUDDHI DEVELOPERS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.