GARGI APARTMENT

MahaRERA P52800034510Caution

by Anil Vithoba Kasar

Survey No. 65/25, 24, 12, Shringartali, 415724

Official record
Dec 2022
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 90.9%.

Official RERA facts

Registration
P52800034510
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

Nilesh Narayan Patil, Nilam Narayan Patil

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2022
Floors
5
Plot / CTS / survey no.
Survey No. 65/25, 24, 12
Planning authority
Others
Approved layout land
700 sq.m
Land for this registration
700 sq.m
Permissible built-up area
648.04 sq.m
Promoter contact
Anil Vithoba Kasar
Registered office
NA
Plot boundaries
North
Adjacent Hissa No 12 and 13
South
Guhagar Bijapur Highway
East
Adjacent Hissa No 26
West
Adjacent Hissa No 24
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • IDBI BANK โ€” 61503
    IFSC IBKL0574RDC
    SAHAKAR BHAVAN,JAWAHAR ROAD,RATNAGIRI,PIN-415612

Commencement Certificate documents

  • Commencement.pdf

Buyer community

Connect with other buyers and owners of GARGI APARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GARGI APARTMENT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.