SHREE COMPLEXMahaRERA P52800047959
Survey No. 282/A1/1A1A1A1/64B, 282/A1/1A1A1A1/63/1, 194/A1A1A1A1A1/3B, 194/A1A1A1A1A1/3A, CTS NO. 2731, 2732, 2733, 2734, Mauje Khed, 415709
- Possession delayed ~1 yr. Originally promised Oct 2025, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52800047959
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally October 2025
- Construction
- 90.6% complete
- Units sold
- 12 of 60
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EA03122518503Revised to December 2026
The delay has occurred as the project plan was revised and the scope of construction work increased, resulting in additional time and resources being required. Therefore, the project could not be completed within the original timeline and an extension is necessary.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Dec 2022
- Floors
- 8
- Unit mix
- 20 res ยท 40 comm
- Architect
- Shrish S Ghorpade
- Plot / CTS / survey no.
- City Survey Number - 2730, 2731, 2732, 2733 & 2734
- Planning authority
- Khed Municipal Council
- Approved layout land
- 724.2 sq.m
- Land for this registration
- 724.2 sq.m
- Permissible built-up area
- 2,544.67 sq.m
- Promoter contact
- Yogesh Shashikant Kudalkar
- Registered office
- Malberry Building
- North
- Gat No 310
- South
- Gat No 324
- East
- Mumbai Goa Highway
- West
- Gat No 311 and 313
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- HDFC BANK โ 48609IFSC HDFC0000146Sharad Kunj, Moose Road, Talao Pali
Commencement Certificate documents
- Commencement Certificate.pdf
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of SHREE COMPLEX โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHREE COMPLEX. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.