KOHINOOR TULIP
by JAIN AND JAIN CONSTRUCTION COMPANY
FINAL PLOT NO. TP SCHEME 02-115/B, ATHAWADA BAZAAR, 415612
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.
Official RERA facts
- Registration
- P52800048970
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2025
- Construction
- 100% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
YOGESH RAGHUVEER PAWASKAR
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jan 2023
- Floors
- 5
- Plot / CTS / survey no.
- FINAL PLOT NO. TP SCHEME 02-115/B
- Planning authority
- Others
- Approved layout land
- 395 sq.m
- Land for this registration
- 395 sq.m
- Permissible built-up area
- 694.76 sq.m
- Registered office
- -
- North
- FINAL PLOT NO 103
- South
- FINAL PLOT NO 115 A
- East
- ROAD
- West
- FINAL PLOT NO 115
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- KOTAK MAHINDRA BANK LIMITED โ 85205IFSC KKBK0001991SHOP NO.4,5&6, VYANKATESH EXECUTIVE MARUTI MANDIR CIRCLE, RATNAGIRI - 415639 MAHARASHTRA
Commencement Certificate documents
- Municipal_permission.pdf
Buyer community
Connect with other buyers and owners of KOHINOOR TULIP โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching KOHINOOR TULIP. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.