PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

MOOSA HERITAGEMahaRERA P52800053064

by MOOSA BUILDERS AND DEVELOPERS

2902/B, 190/A/1/12, KHED, 415709

Jun 2026
Possession
57.7%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 57.7%.

Official RERA facts

Registration
P52800053064
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
57.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Water linenot started
UGWTnot started
Parking Blocknot started
Entrance Gatenot started

Building & registration

RERA registered
Oct 2023
Floors
7
Plot / CTS / survey no.
2902/B, 190/A/1/12
Planning authority
Others
Approved layout land
797.43 sq.m
Land for this registration
797.43 sq.m
Permissible built-up area
2,387.49 sq.m
Registered office
CHIKTE COMPLEX
Plot boundaries
North
2902 A
South
2901 A
East
2903 A1 2903 A2 2903 B
West
NAGARPRISHD ROAD
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • KOTAK MAHINDRA BANK LIMITED โ€” 86607
    IFSC KKBK0KMCB02
    MAHADIK MOHALLA PAWASKAR NAKA KHED DIST RATNAGIRI 415709

Commencement Certificate documents

  • C C MOOSA.pdf
  • Moosa CC Verification.pdf

Buyer community

Connect with other buyers and owners of MOOSA HERITAGE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MOOSA HERITAGE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.