PASHCHIMAMahaRERA P52800077099
Survey No.91/5, 89A/4 and 11,CTS No.493,494,495,496,497,498,499,500,501,502,503,1196 and 1553, Guhagar, 415703
- Behind schedule. Possession is due Oct 2026 but construction is only at 46.8%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.
Official RERA facts
- Registration
- P52800077099
- Status
- New
- Stage
- Certificate Signed
- Possession
- October 2026
- Construction
- 46.8% complete
- Units sold
- 9 of 25
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jul 2024
- Floors
- 4
- Unit mix
- 8 res ยท 17 comm
- Architect
- Rita Paranjape
- Plot / CTS / survey no.
- Survey No.91/5, 89A/4 and 11,CTS No.493,494,495,496,497,498,499,500,501,502,503,1196 and 1553
- Planning authority
- Guhagar Nagar Panchayat (Municipal Council)
- Approved layout land
- 1,323.7 sq.m
- Land for this registration
- 1,323.7 sq.m
- Permissible built-up area
- 2,637.87 sq.m
- Promoter contact
- MAKARAND GAJANAN KHARE
- Registered office
- Guhagar
- North
- Hotel Vainatey
- South
- Panchayat Samiti Office
- East
- S T Stand
- West
- Guhagar - Asagoli Road
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- CANARA BANK โ 34079IFSC CNRB0005638At post Guhagar, Tal Guhagar, Dist Ratnagiri 415703
Commencement Certificate documents
- 2 Commencement Certificates _ NA Order for plotted development_page-0001 - Copy.pdf
- New Permission.pdf
Buyer community
Connect with other buyers and owners of PASHCHIMA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching PASHCHIMA. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.