Under construction

MANORAMA COMPLEXMahaRERA P52900006912

by KEDAR CONSTRUCTION

5251, 5252, 5253, 5254, 5255, Sawantwadi (M Cl), 416510

Dec 2021
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2021 per the RERA filing.

Official RERA facts

Registration
P52900006912
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021originally December 2019
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths45%
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Water50%

Building & registration

RERA registered
Aug 2017
Floors
7

Buyer community

Connect with other buyers and owners of MANORAMA COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MANORAMA COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.