Under construction

SONBAHAVA - PHASE 2MahaRERA P52900007661

by Mega Realtors

108/3 AND 110, Majgaon (CT), 416510

Sept 2018
Possession
55.2%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Sept 2018) has passed with construction at 55.2%.

Official RERA facts

Registration
P52900007661
Status
Ongoing
Stage
Certificate Signed
Possession
September 2018
Construction
55.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths75%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting60%
Street Lighting20%
Community Buildings80%
Electrical meter room, sub-station, receiving station10%
Aggregate area of recreational Open Space30%

Building & registration

RERA registered
Aug 2017
Floors
2

Buyer community

Connect with other buyers and owners of SONBAHAVA - PHASE 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SONBAHAVA - PHASE 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.