Jun 2027
Possession
16.5%
Built
0
Complaints
181
Units
High risk
  • Behind schedule. Possession is due Jun 2027 but construction is only at 16.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52900009547
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027
Construction
16.5% complete
Units sold
13 of 181

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
8
Unit mix
134 res ยท 47 comm
Architect
NAVIN LAD

Buyer community

Connect with other buyers and owners of ASHTVINAYAK GRUHSANKUL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ASHTVINAYAK GRUHSANKUL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.