Kshitij Market City Phase IMahaRERA P52900010519
381 B,381 K,403,1515,1297,404,406,407,408,409,410,674,675,1428 TO 1433,314 A5, Kudal (CT), 416520
- Possession delayed ~1 yr. Originally promised Dec 2019, now proposed Jan 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Jan 2021) has passed with construction at 23.6%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jan 2021 per the RERA filing.
Official RERA facts
- Registration
- P52900010519
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- January 2021originally December 2019
- Construction
- 23.6% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2017
- Floors
- 9
Buyer community
Connect with other buyers and owners of Kshitij Market City Phase I โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Kshitij Market City Phase I. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.