Under construction

Shivaji ParkMahaRERA P52900010548

by AAradhya Landmarks & Infra Pvt. Ltd.

Survey No.221 Hissa No. 3,5, 7A2, 7B Survey No.222 Hissa No. 27, Kudal (CT), 416520

Dec 2021
Possession
79.6%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 79.6%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2021 per the RERA filing.

Official RERA facts

Registration
P52900010548
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
79.6% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths15%
Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drains10%
Landscaping & Tree Plantingnot started
Street Lighting10%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water10%
Solid Waste Management And Disposal15%
Water conservation /Rain water harvesting10%
Fire protection and fire safety requirements10%
Electrical meter room, sub-station, receiving station25%
Aggregate area of recreational Open Space10%
Open Parking15%

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of Shivaji Park โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shivaji Park. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.