All RERA projects
๐๏ธ
Under construction
AJINKYA ROYALMahaRERA P52900015368
S NO 68A H NO 6, 9A, 9B, 13 , CTS NOS. 170,171,172,173,174,175,176,177,178,179, SABNISWADA, 416510
Feb 2022
Possession
90.9%
Built
0
Complaints
0
Units
Caution
- Possession date passed. The proposed possession date (Feb 2022) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P52900015368
- Status
- New
- Stage
- Certificate Signed
- Possession
- February 2022
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Building & registration
- RERA registered
- Feb 2018
- Floors
- 6
Buyer community
Connect with other buyers and owners of AJINKYA ROYAL โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AJINKYA ROYAL. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.