OTRA PRESTIGEMahaRERA P52900015540
SURVEY NO 123-38A1,40A 1,41-1,43-1, RAWALNATH NAGAR, 416812
Jan 2029
Possession
32%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~5 yrs. Originally promised Jan 2024, now proposed Jan 2029 per the RERA filing.
Official RERA facts
- Registration
- P52900015540
- Status
- New
- Stage
- Certificate Signed
- Possession
- January 2029originally January 2024
- Construction
- 32% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Mar 2018
- Floors
- 5
Buyer community
Connect with other buyers and owners of OTRA PRESTIGE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching OTRA PRESTIGE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.