Under construction

OTRA PRESTIGEMahaRERA P52900015540

by OTRA REALTY LLP

SURVEY NO 123-38A1,40A 1,41-1,43-1, RAWALNATH NAGAR, 416812

Jan 2029
Possession
32%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Jan 2024, now proposed Jan 2029 per the RERA filing.

Official RERA facts

Registration
P52900015540
Status
New
Stage
Certificate Signed
Possession
January 2029originally January 2024
Construction
32% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2018
Floors
5

Buyer community

Connect with other buyers and owners of OTRA PRESTIGE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching OTRA PRESTIGE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.