MAITRI GARDENMahaRERA P52900015714
S NO 143B15, KANAK NAGAR, 416602
Jun 2028
Possession
49.1%
Built
0
Complaints
118
Units
High risk
- Possession delayed ~6 yrs. Originally promised Dec 2022, now proposed Jun 2028 per the RERA filing.
Official RERA facts
- Registration
- P52900015714
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2028originally December 2022
- Construction
- 49.1% complete
- Units sold
- 9 of 118
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting30%
Energy managemcntnot started
Fire protection and fire safety requirements35%
Electrical meter room, sub-station, receiving station35%
Open Parkingnot started
Building & registration
- RERA registered
- Mar 2018
- Floors
- 9
- Unit mix
- 112 res ยท 6 comm
- Architect
- AR.V.N.KAMAT
Buyer community
Connect with other buyers and owners of MAITRI GARDEN โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MAITRI GARDEN. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance