PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

GODGRESS AMahaRERA P52900017282

by GODGRESS

500A, 6d1, Jamsande, 416612

Dec 2024
Possession
59.1%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2019, now proposed Dec 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 59.1%.

Official RERA facts

Registration
P52900017282
Status
New
Stage
Certificate Signed
Possession
December 2024originally December 2019
Construction
59.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2018
Floors
3

Buyer community

Connect with other buyers and owners of GODGRESS A โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GODGRESS A. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.