AXIS BLUESMahaRERA P52900019883
by EEJAK HOLDINGS PRIVATE LIMITED
434, 435, 436, 437, 448, 449, Yog City, 416512
Dec 2027
Possession
65%
Built
9
Complaints
128
Units
High risk
- Possession delayed ~4 yrs. Originally promised May 2024, now proposed Dec 2027 per the RERA filing.
- 9 RERA complaints. 9 complaint records are disclosed against this project on MahaRERA.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P52900019883
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally May 2024
- Construction
- 65% complete
- Units sold
- 69 of 128
RERA complaint record9 records
- ComplaintCC1260434411 Jul 2026Smitha Madhusudan Shetty vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC1260382920 Jun 2026Mansoor Changankattil vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC126035629 Jun 2026Priyanka Ulavakayala vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC1260310625 May 2026Ranganath Joseph Kallubhavi vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC1260298320 May 2026Zakir Hussain vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC126026878 May 2026Sunil Lowanshi vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC126011995 Mar 2026Asadkhan Alisherkhan Pathan vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC1250349830 Sept 2025Rishikesh Deodas Gajbhiye vs EEJAK HOLDINGS PRIVATE LIMITEDS62 CC12503498.pdf on MahaRERA
- ComplaintCC1250201119 Jun 2025Perugu Anusha vs EEJAK HOLDINGS PRIVATE LIMITED
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Mar 2019
- Floors
- 5
- Unit mix
- 121 res ยท 7 comm
Buyer community
Connect with other buyers and owners of AXIS BLUES โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AXIS BLUES. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.