Under construction
AXIS YOG VILLASMahaRERA P52900021552
by ARUSH INFRA PROMOTERS PRIVATE LIMITED
505, 506, 507, 511, 512, 513, Yog City, 416512
May 2027
Possession
2.3%
Built
1
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Jul 2024, now proposed May 2027 per the RERA filing.
- Behind schedule. Possession is due May 2027 but construction is only at 2.3%.
Official RERA facts
- Registration
- P52900021552
- Status
- New
- Stage
- Certificate Signed
- Possession
- May 2027originally July 2024
- Construction
- 2.3% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC1260321128 May 2026Navaneet Kumar Sharma vs ARUSH INFRA PROMOTERS PRIVATE LIMITED
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Building & registration
- RERA registered
- Jul 2019
- Floors
- 2
Buyer community
Connect with other buyers and owners of AXIS YOG VILLAS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AXIS YOG VILLAS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.