PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

AXIS BLUESMahaRERA P52900021725

by EEJAK HOLDINGS PRIVATE LIMITED

432, 433,438,439, 446, 447, Yog Resort, 416512

Dec 2027
Possession
59%
Built
10
Complaints
128
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Jul 2024, now proposed Dec 2027 per the RERA filing.
  • 10 RERA complaints. 10 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52900021725
Status
New
Stage
Certificate Signed
Possession
December 2027originally July 2024
Construction
59% complete
Units sold
105 of 128

RERA complaint record10 records

  • ComplaintCC1260442216 Jul 2026
    Deepa Patil vs EEJAK HOLDINGS PRIVATE LIMITED
  • ComplaintCC126033591 Jun 2026
    Mahesh Rampur vs EEJAK HOLDINGS PRIVATE LIMITED
  • ComplaintCC1260321028 May 2026
    Viddhesh Hanumant Belgaonkar vs EEJAK HOLDINGS PRIVATE LIMITED
  • ComplaintCC1260310825 May 2026
    Gibin Gipson George vs EEJAK HOLDINGS PRIVATE LIMITED
  • ComplaintCC1260304923 May 2026
    Colleta Ruby Vaz vs EEJAK HOLDINGS PRIVATE LIMITED
  • ComplaintCC1260294319 May 2026
    Azaz Nizamuddin Khan vs EEJAK HOLDINGS PRIVATE LIMITED
  • ComplaintCC1260275711 May 2026
    Thudukurthi Prasanth Kumar vs EEJAK HOLDINGS PRIVATE LIMITED
  • ComplaintCC126026507 May 2026
    SITA PRABHU DESSAI vs EEJAK HOLDINGS PRIVATE LIMITED
  • ComplaintCC1260089218 Feb 2026
    Nidhi Mishra vs EEJAK HOLDINGS PRIVATE LIMITED
  • ComplaintCC125018606 Jun 2025
    VINCENT LEWIS vs EEJAK HOLDINGS PRIVATE LIMITED
    roznama 21- Disposed Off on consent term SIGNED.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2019
Floors
5
Unit mix
121 res ยท 7 comm

Buyer community

Connect with other buyers and owners of AXIS BLUES โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AXIS BLUES. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.