ADITYASAGAR COMPLEX PHASE IIMahaRERA P52900029896

by Siddhesh Mahadeo Kanade

R.S.No. 38A Hissa No. 3A, Sambhaji Chowk, 416810

Dec 2026
Possession
79%
Built
0
Complaints
18
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52900029896
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
79% complete
Units sold
10 of 18

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

Mr Shantanu Ramakant Narkar

Possession extension history

  • EXT52900018655Revised to December 2024

    I have registered my Real Estate Project under MahaRERA on 12/07/2021. Due to heavy rainfall in Kokan area and market condition and slow response from the buyers I have started development work of the Project in the year 2022. That I have completed 45% project work and the Project RCC 80% completed and other work of the project is in progress. Hence I haven’t been able to complete the project in the scheduled time i.e. on 31/12/2023. I request MahaRERA authority please grant me extension up to 30th December 2024 for the completion of the project

  • EXT52900025872Revised to December 2025

    The project work means the slab is completed and the electrical fittings and internal external work is going on. Due to heavy rains in Konkan, the work of the project stops for 3 months in a year. I am unable to complete the project on time. Therefore, I request the MahaRERA authority to kindly approve the extension of my project at the earliest.

  • EA21032620317Revised to December 2026

    The project work is in progress. The work related to the lift, sanitary fittings, doors and windows, staircase, lobby, electrical meter room, and substation is expected to be completed by the end of May 2026. Thereafter, we will apply for the Completion Certificate. Upon receipt of the Completion Certificate, the same will be updated in the project.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Planting90%
Treatment And Disposal Of Sewage And Sullage Water90%
Water conservation /Rain water harvesting90%
Energy managemcnt90%
Electrical meter room, sub-station, receiving station90%

Building & registration

RERA registered
Jul 2021
Floors
2
Unit mix
18 res · 0 comm
Architect
Sunil Digambar Kulkarni
Plot / CTS / survey no.
R.S.No. 38A Hissa No. 3A
Planning authority
Vabhave Vaibhavwadi Nagarpanchayat
Approved layout land
2,973 sq.m
Land for this registration
2,973 sq.m
Permissible built-up area
1,290.62 sq.m
Promoter contact
Siddhesh Mahadeo Kanade
Registered office
Adityasagar
Plot boundaries
North
Hissa No 3 B
South
Internal Road
East
Gaganbawada Tarale road
West
Hissa No 4

Project bank account

The RERA-designated account this project's payments should go to — verify before wiring any money.

  • STATE BANK OF INDIA — 122708
    IFSC SBIN0011157
    Vaibhavwadi District-Sindhudurg

Commencement Certificate documents

  • Commencement certificate_compressed.pdf

Buyer community

Connect with other buyers and owners of ADITYASAGAR COMPLEX PHASE II — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching ADITYASAGAR COMPLEX PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.