DYANESHWARIMahaRERA P52900048563
by DDS BUILDCON
C.T.S. No. 2348A, Kelbaiwadi Kudal, 416520
- Behind schedule. Possession is due Dec 2026 but construction is only at 41.6%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52900048563
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 41.6% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
Rupali Rajendra Pawar
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jan 2023
- Floors
- 8
- Plot / CTS / survey no.
- C.T.S. No. 2348A
- Planning authority
- Kudal Nagar Panchayat
- Approved layout land
- 1,713 sq.m
- Land for this registration
- 1,713 sq.m
- Permissible built-up area
- 3,860.18 sq.m
- Registered office
- NA
- North
- C T S No 2349
- South
- ROAD
- East
- C T S No 2348B
- West
- ROAD
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- SARASWAT COOPERATIVE BANK LIMITED โ 143259IFSC SRCB0000220Pratham Apartment, Opp Kudal High School Kudal, Vengurla Road, Tal Kudal, Dist Sindhudurg
Commencement Certificate documents
- Commencement Certificate Certificate.pdf
- Commencement Certificate.pdf
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of DYANESHWARI โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching DYANESHWARI. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.