๐Ÿ—๏ธ
Under construction

MANOMAY RESIDENCYMahaRERA P52900052174

by SUMUKH DEVELOPERS

48/6/10,11,12, KUDAL, 416520

Dec 2026
Possession
63.6%
Built
0
Complaints
27
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52900052174
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
63.6% complete
Units sold
7 of 27

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2023
Floors
6
Unit mix
22 res ยท 5 comm
Plot / CTS / survey no.
48/6/10,11,12
Planning authority
KUDAL NAGAR PANCHAYAT
Approved layout land
731 sq.m
Land for this registration
731 sq.m
Recreational open space
731 sq.m
Permissible built-up area
1,685.72 sq.m
Registered office
MEHNIAL PLAZA
Plot boundaries
North
SURVEY NO 48 HISSA NO 6 3
South
SURVEY NO 48 HISSA NO 6 13
East
SURVEY NO 51
West
SURVEY NO 48 HISSA NO 6 9
Parking
5 four-wheeler16 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • BANK OF INDIA โ€” 15473
    IFSC BKID0001471
    AT AND POST KUDAL 416520

Commencement Certificate documents

  • COMMENCEMENT CERTIFICATE.pdf

Buyer community

Connect with other buyers and owners of MANOMAY RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MANOMAY RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.