AYAANS AMBARYMahaRERA P52900053470

by Suman Developers

Survey No 1022, Hissa No 8/2, CTS No 2301,2302, Malvan, 416606

Jun 2027
Possession
59.3%
Built
0
Complaints
57
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52900053470
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2026
Construction
59.3% complete
Units sold
11 of 57

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

Meera Dayanand Saraf

Possession extension history

  • EA09092502540Revised to June 2027

    The extension is essential to maintain the validity of the project registration, without the extension, the registration will lapse, which will: Halt ongoing construction work. Stall disbursement of home loans by banks / financial institutions. Prevent registration of new agreements for sale. Result in severe cash flow disruption, adversely affecting allottees. The project has been delayed due to circumstances beyond the control of the Promoter, such as: Shortage of labour and demand slump triggered by market volatility. Unavailability of skilled labour and labour migration issues, leading contractors to seek additional time. Financial stress on allottees resulting in huge receivables pending from them, thereby over the past few years, coupled with rising construction costs. Financial stress on allottees resulting in huge receivables pending from them, thereby affecting the Promoter’s cash flows and financial position. Despite these unforeseen challenges, the Promoter remains fully committed to the timely and efficient completion of the project, with continued focus on quality and adherence to regulatory norms. In view of the above exceptional and genuine circumstances, the Promoter respectfully seeks an extension of the project completion timeline, as detailed in Form B, in the interest of both the allottees and the overall success of the project.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Nov 2023
Floors
8
Unit mix
42 res · 15 comm
Architect
AR Akshay Ashok Bhojane Bhojane
Plot / CTS / survey no.
Survey No 1022, Hissa No 8/2, CTS No 2301,2302
Planning authority
MALVAN MUNICIPAL COUNCIL
Approved layout land
940 sq.m
Land for this registration
940 sq.m
Permissible built-up area
3,266.36 sq.m
Registered office
Shop No 2
Plot boundaries
North
Muncipal Road
South
CTS No 2292 PROPERTY OF Mr NAIK
East
CTS No 2308 and CTS No 2303
West
CTS No 2300 UPCOMING MIXED USE PROJECT
Parking

Project bank account

The RERA-designated account this project's payments should go to — verify before wiring any money.

  • SARASWAT COOPERATIVE BANK LIMITED — 143145
    IFSC SRCB0000040
    Madhu Sindhu Malvan Sindhudurg 416606

Commencement Certificate documents

  • CC.pdf

Buyer community

Connect with other buyers and owners of AYAANS AMBARY — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching AYAANS AMBARY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.