Under construction

JUNCTION 176MahaRERA P53000000545

by Bhima builders & developers

176, Kolhapur (M Corp.), 416002

Dec 2021
Possession
66.4%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 66.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2021 per the RERA filing.

Official RERA facts

Registration
P53000000545
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
66.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposal90%
Water conservation /Rain water harvesting90%
Energy managemcntnot started
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station80%

Building & registration

RERA registered
Jul 2017
Floors
11

Buyer community

Connect with other buyers and owners of JUNCTION 176 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching JUNCTION 176. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.