PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ROYAL MIRAJ ARCADEMahaRERA P53000002279

by Vishwas Bajirao Patil

C S NO 340, Opp. Railway Station, 416001

Jun 2024
Possession
75.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2022, now proposed Jun 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 75.9%.

Official RERA facts

Registration
P53000002279
Status
Ongoing
Stage
Certificate Signed
Possession
June 2024originally December 2022
Construction
75.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jul 2017
Floors
11

Buyer community

Connect with other buyers and owners of ROYAL MIRAJ ARCADE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ROYAL MIRAJ ARCADE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.