Under construction

Pinnac ShivalayaMahaRERA P53000003090

by Suresh Rajaram Dharmadhikari

CTS No - 1764A/3A, A-Ward, -, 416012

Jun 2027
Possession
81.3%
Built
0
Complaints
19
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2019, now proposed Jun 2027 per the RERA filing.

Official RERA facts

Registration
P53000003090
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027originally December 2019
Construction
81.3% complete
Units sold
14 of 19

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station90%

Building & registration

RERA registered
Aug 2017
Floors
8
Unit mix
19 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Pinnac Shivalaya โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Pinnac Shivalaya. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.