Dwarka RavajiMahaRERA P53000005706
by M/S Randive Builders and Developers
Plot No 79 Part and 80 C S No 1574 and 1573, Kolhapur (M Corp.), 416008
- Possession delayed ~2 yrs. Originally promised Feb 2021, now proposed Feb 2023 per the RERA filing.
- Possession date passed. The proposed possession date (Feb 2023) has passed with construction at 75.6%.
The airport-bet frontier โ golf course, hills and heavy new supply.
- Growth drivers:
- Navi Mumbai International Airport, MTHL access, NAINA planning zone.
- Who buys here:
- First-time buyers and investors betting on the airport economy.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P53000005706
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- February 2023originally February 2021
- Construction
- 75.6% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2017
- Floors
- 8
Buyer community
Connect with other buyers and owners of Dwarka Ravaji โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Dwarka Ravaji. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.