LIFE MONTAGE PHASE 2
SR. NO 214. HISSA NO 3, VILLAGE - SUS, TALUKA - MULSHI, DISTRICT - PUNE, STATE MAHARASHTRA, SUS, 411021
- Possession delayed ~1 yr. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 48.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2020 per the RERA filing.
Official RERA facts
- Registration
- P53000006727
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2020originally June 2019
- Construction
- 48.2% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2017
- Floors
- 16
Buyer community
Connect with other buyers and owners of LIFE MONTAGE PHASE 2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching LIFE MONTAGE PHASE 2. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.