SKYLINE TOWER CMahaRERA P53000009065
2807/2, Kadamwadi, 416003
Dec 2026
Possession
90.7%
Built
1
Complaints
38
Units
Caution
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P53000009065
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2024
- Construction
- 90.7% complete
- Units sold
- 25 of 38
RERA complaint record1 record
- ComplaintCC1240109110 Dec 2024Sudhir Sadashiv Desai vs SAIBHAGWANT DEVELOPERSLOP srno20 signed.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)98%
Storm Water Drainsdone
Landscaping & Tree Planting98%
Water conservation /Rain water harvesting98%
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving station95%
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 11
- Unit mix
- 38 res ยท 0 comm
- Architect
- MR SANJAY A ADAKE
Buyer community
Connect with other buyers and owners of SKYLINE TOWER C โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SKYLINE TOWER C. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.