PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

VASANT SAPTAMahaRERA P53000017602

by Chougule hosmani Construction

R S No 580/Plot No 13,14,15,/1 to 7, Near Gas Pump, 416004

Mar 2021
Possession
69.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2021) has passed with construction at 69.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2021 per the RERA filing.

Official RERA facts

Registration
P53000017602
Status
New
Stage
Certificate Signed
Possession
March 2021
Construction
69.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started

Building & registration

RERA registered
Aug 2018
Floors
3

Buyer community

Connect with other buyers and owners of VASANT SAPTA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VASANT SAPTA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.