Under construction
Atharva Sky Line Wing-BMahaRERA P53000023030
R.S.No. 156/4, Ujalaiwadi, 416005
Dec 2026
Possession
90.1%
Built
0
Complaints
84
Units
Caution
- Possession delayed ~2 yrs. Originally promised Nov 2024, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P53000023030
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally November 2024
- Construction
- 90.1% complete
- Units sold
- 62 of 84
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply94%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains97%
Water conservation /Rain water harvesting95%
Energy managemcnt80%
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving station97%
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Nov 2019
- Floors
- 14
- Unit mix
- 84 res ยท 0 comm
- Architect
- Vision Associates Through Prashant Kapdi
Buyer community
Connect with other buyers and owners of Atharva Sky Line Wing-B โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Atharva Sky Line Wing-B. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.