Under construction

BALVANT PLAZAMahaRERA P53000023063

by jahir chandsab saudagar

RCS NO 673 B 2 1755 PART, NEAR ABHISHEK MANGAL KARYALAYA, 416115

Nov 2024
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Sept 2023, now proposed Nov 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Nov 2024) has passed with construction at 90.9%.

Official RERA facts

Registration
P53000023063
Status
New
Stage
Certificate Signed
Possession
November 2024originally September 2023
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Nov 2019
Floors
7

Buyer community

Connect with other buyers and owners of BALVANT PLAZA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BALVANT PLAZA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.