Under construction

MANJULA PLAZAMahaRERA P53000023946

by BALAJI CONSTRUCTION

356/5B, Back side of Taluka Court, 416502

Dec 2023
Possession
90.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 90.5%.

Official RERA facts

Registration
P53000023946
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
90.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving station96%

Building & registration

RERA registered
Jan 2020
Floors
4

Buyer community

Connect with other buyers and owners of MANJULA PLAZA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MANJULA PLAZA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.