CLYDE HOMES phase2MahaRERA P53000026035
RS NO 209A/1 HISSA NO 1K/1 AND 1K/2, TARABAI PARK, 416003
- Possession date passed. The proposed possession date (Aug 2024) has passed with construction at 49.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2024 per the RERA filing.
Official RERA facts
- Registration
- P53000026035
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2024
- Construction
- 49.3% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2020
- Floors
- 19
- Plot / CTS / survey no.
- RS NO 209A/1 HISSA NO 1K/1 AND 1K/2
- Planning authority
- Others
- Approved layout land
- 3,720 sq.m
- Land for this registration
- 3,720 sq.m
- Permissible built-up area
- 14,040 sq.m
- Registered office
- Varad Residency
- North
- RS NO 208
- South
- 12M WIDE
- East
- RS NO 209A1 HISSA NO 2
- West
- RS NO 209A1 HISSA NO 1K3 AND 1K5
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- BANK OF BARODA โ 10343IFSC BARB0TARABASAYANTARA COMPLEX, E WARD, NAGALA PARK, KOLHAPUR
Commencement Certificate documents
- COMMENCEMENT CERTIFICATE(1).pdf
- commencement Certificate Clyde Homes C-Wing_compressed.pdf
Buyer community
Connect with other buyers and owners of CLYDE HOMES phase2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching CLYDE HOMES phase2. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.