Padam Pooja SarovarMahaRERA P53000026226
by Pratik Oswal
633/1,2,8,9,16,17/1,17/2,18,19,20,23,24,26,28, Jawahar Nagar, 416012
- Behind schedule. Possession is due Jun 2027 but construction is only at 19.7%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P53000026226
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027
- Construction
- 19.7% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2020
- Floors
- 4
- Plot / CTS / survey no.
- 633/1,2,8,9,16,17/1,17/2,18,19,20,23,24,26,28
- Planning authority
- Others
- Approved layout land
- 7,900 sq.m
- Land for this registration
- 7,900 sq.m
- Recreational open space
- 610 sq.m
- Permissible built-up area
- 4,460 sq.m
- Registered office
- Padam Pooja Sarovar
- North
- rs no 634
- South
- 18m dp road
- East
- 12 m dp road
- West
- Jayanti Nala
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- IDBI BANK โ 59046IFSC IBKL0000665tarabai park
Commencement Certificate documents
- PPS CC.pdf
Buyer community
Connect with other buyers and owners of Padam Pooja Sarovar โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Padam Pooja Sarovar. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.