PLOT NO.2 OUT OF R.S.NO.900/5/A, DEVKAR PANAND, 416012
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 63.4%.
Official RERA facts
- Registration
- P53000046636
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026
- Construction
- 63.4% complete
- Units sold
- 11 of 14
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2022
- Floors
- 2
- Unit mix
- 14 res ยท 0 comm
- Architect
- ASSOCIATED ENGINEERS
- Plot / CTS / survey no.
- PLOT NO.2 OUT OF R.S.NO.900/5/A
- Planning authority
- Kolhapur Municipal Corporation
- Approved layout land
- 1,378 sq.m
- Land for this registration
- 1,378 sq.m
- Permissible built-up area
- 1,360.55 sq.m
- Promoter contact
- OMKAR SHIRISH KANERKAR
- Registered office
- --
- North
- R S NO 899 900-4 AND 901
- South
- 9 METER ROAD AND R S NO 900-5B
- East
- CORPORATION OPEN SPACE OUT OF R S NO 900-5
- West
- PLOT NO 1 OUT OF R S NO 900-5
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- NKGSB COOPERATIVE BANK LIMITED โ 93782IFSC NKGS0000066A WARD NALE COLONY KALAMBA ROAD KOLHAPUR
Commencement Certificate documents
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of OM RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching OM RESIDENCY. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.