PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

GREVILLEA INITIATIVE BY BHIMRAO JOCKEYMahaRERA P53000050773

by M/S JOTIRADITYA BUILDERS

C. S. No.T.P. Scheme No.2 Final Plot No.88, Dudhali, 416012

Dec 2026
Possession
84.5%
Built
1
Complaints
35
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P53000050773
Status
New
Stage
Certificate Signed
Possession
December 2026originally March 2025
Construction
84.5% complete
Units sold
21 of 35

RERA complaint record1 record

Landowner

Smt Rohini Rajaram Jadhav, Shri Ajit Rajaram Jadhav, Sou Shital Sandeep Jadhav, Shri Ashok Bhimrao Jadhav, Shri Dilip Bhimrao Jadhav, Smt Pushma Bhinrao Jadhav, Mr Prakash Bhimrao Jadhav

Possession extension history

  • EXT53000027850Revised to December 2025

    The Construction work of our project is going on. We need 4 to 5 months to complete the all construction work and to receive completion certificate from Kolhapur Municipal Corporation. Hence we have apply for extension till 31/12/2025. We Request the Authority to Please grant us extension till 31/12/2025. We will assure that we will upload Full occupancy Certificate before 31/12/2025 on RERA Portal.

  • EA23022619964Revised to December 2026

    We completed our entire construction work. We submit all the NOC or documents to Kolhapur Municipal corporation for completion certificate on --- but we have no get completion certificate from competent Authority hence applied for extension till Sep 2026. We request the Authority please grant us extension till date 31/12/2026.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2023
Floors
8
Unit mix
35 res ยท 0 comm
Architect
globita assiciates
Plot / CTS / survey no.
C. S. No.T.P. Scheme No.2 Final Plot No.88
Planning authority
Kolhapur Municipal Corporation
Approved layout land
1,080 sq.m
Land for this registration
1,080 sq.m
Permissible built-up area
3,454.86 sq.m
Registered office
--
Plot boundaries
North
Final Plot No 80
South
Final Plot No 87
East
Garden
West
9 Mtr Road
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • RAJARAMBAPU SAHAKARI BANK LIMITED โ€” 111290
    IFSC RRBP0000037
    Mangalwar Peth Kolhapur

Commencement Certificate documents

  • BUILDING PERMITION.pdf
  • Commencement Cetificate.pdf

Buyer community

Connect with other buyers and owners of GREVILLEA INITIATIVE BY BHIMRAO JOCKEY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GREVILLEA INITIATIVE BY BHIMRAO JOCKEY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.