HARIPRIYA SANKULMahaRERA P53000052036
by DATTA SAI BUILDERS AND DEVELOPERS
R.S.NO.714B/2, NIRMAN CHOWK, 416012
No delays, complaints or enforcement actions in the official disclosures we track.
Official RERA facts
- Registration
- P53000052036
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally March 2026
- Construction
- 65.7% complete
- Units sold
- 30 of 69
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
VYANKTESHWARA CONSTRUCTIONS
Possession extension history
- EXT53000024084Revised to March 2027
Built up area is increased due to recent revision of plan resulting in delay.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jul 2023
- Floors
- 12
- Unit mix
- 44 res ยท 25 comm
- Architect
- RAHUL SASANE
- Plot / CTS / survey no.
- R.S.NO.714B/2
- Planning authority
- Kolhapur Municipal Corporation
- Approved layout land
- 1,300 sq.m
- Land for this registration
- 1,300 sq.m
- Permissible built-up area
- 3,416.52 sq.m
- Registered office
- Mirajkar Heights
- North
- 100 FEET ROAD
- South
- CHATRAPATI SHAHU GRAH NIRMAN SANTHA
- East
- 714B
- West
- 714A
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- IDBI BANK โ 59019IFSC IBKL00006341014 A WARD,KHARI CORNER,KOLHAPUR
Registered agents
- VaishnaviSandeep MirajkarA011152501830 ยท 8446848848
Commencement Certificate documents
- 7_Commencement Certificate(Prarambh Cert).pdf
- sudharit badhkam parvana_compressed.pdf
Buyer community
Connect with other buyers and owners of HARIPRIYA SANKUL โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching HARIPRIYA SANKUL. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.