SHREE SAMARTH HEIGHTS
TPS 1 - PLOT NO 57, GADHINGLAJ, 416502
- Possession delayed ~2 yrs. Originally promised Apr 2025, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P53000052425
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally April 2025
- Construction
- 53.2% complete
- Units sold
- 9 of 72
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
HANMAMT LAXMAN PATHARVAT, NISHIKANT GANPATRAO CHOTHE, VIMAL SURESH PATIL, VIRAPPA SONABA MORTI, VISHWANATH GANPATI SHINTRE, SHRIPATI RANABA SUTAR
Possession extension history
- EA26052501256Revised to December 2026
Dear Sir/Ma’am, We, Shree Samarth Heights, hereby declare the following with respect to the project “Shree Samarth Heights” bearing registration number P53000052425 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 80% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Occupation Certificate (OC) promptly. We anticipate receiving the OC before 31st December 2026. 3. Consent from Allottees: We have obtained consent from 100% of the allottees, indicating their support for the extension request and the continuation of the project towards timely completion. 4. Reason for Delay: The delay in completion has been due to unforeseen challenges, Despite these hurdles, we have maintained steady progress and are now in the final stages of the project. 5. Attached herewith the CPM Report and detailed project planning schedule outlining the timeline and milestones for completing the remaining work. 6. Request for Extension: In view of the above, we respectfully request an extension of the project completion timeline to ensure a smooth transition and timely delivery to our valued allottees. This extension will enable us to complete all pending works with due diligence and quality standards. We sincerely urge you to grant the requested extension, which is crucial for the successful completion of the project and to uphold the commitments made to our allottees.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2023
- Floors
- 7
- Unit mix
- 27 res · 45 comm
- Architect
- GORULE ARCHITECTS
- Plot / CTS / survey no.
- TPS 1 - PLOT NO 57
- Planning authority
- GADHINGLAJ MUNCIPAL COUNSIL
- Approved layout land
- 1,111.42 sq.m
- Land for this registration
- 1,111.42 sq.m
- Permissible built-up area
- 3,392.02 sq.m
- Registered office
- SHIVLRUPA
- North
- PLOT
- South
- WIDE ROAD
- East
- CHANDGAD ROAD
- West
- PLOT
Project bank account
The RERA-designated account this project's payments should go to — verify before wiring any money.
- IDBI BANK — 59466IFSC IBKL0001174BADYACHI WADI GADHINGLAJ
Commencement Certificate documents
- BUILDING PERMISSION.pdf
- plinth certificate.pdf
Buyer community
Connect with other buyers and owners of SHREE SAMARTH HEIGHTS — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet — start one and connect with the next buyer researching SHREE SAMARTH HEIGHTS. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.