JOY PALACEMahaRERA P53000077135
by A.B.Lokhande Builder and Developer
R.S.No.827/1 Final Plot No.10/1, Mouje Kasaba Bawada, 416003
- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 86.4%.
Official RERA facts
- Registration
- P53000077135
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2025
- Construction
- 86.4% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jul 2024
- Floors
- 4
- Plot / CTS / survey no.
- R.S.No.827/1 Final Plot No.10/1
- Planning authority
- Others
- Approved layout land
- 515 sq.m
- Land for this registration
- 515 sq.m
- Permissible built-up area
- 905.88 sq.m
- Promoter contact
- Amit Bapu Lokhande
- Registered office
- Joy Residency
- North
- Colony Road and Plot No 11
- South
- Property Of R S no 826
- East
- Plot No 10
- West
- Property of R S No 828
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- IDBI BANK โ 59046IFSC IBKL0000665C S No 260/7 E ward Near Kiran Bungalow Kolhapur416001
Commencement Certificate documents
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of JOY PALACE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching JOY PALACE. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.