BARSANA RESIDENCYMahaRERA P53100000238

by AKSHADA YOGESH CHAVAN

488/1/3 / PLOT NO.1, Savarkar Nagar, 415311

Feb 2019
Possession
72.7%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Feb 2019) has passed with construction at 72.7%.

Official RERA facts

Registration
P53100000238
Status
Ongoing
Stage
Certificate Signed
Possession
February 2019originally February 2018
Construction
72.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Jul 2017
Floors
5

Buyer community

Connect with other buyers and owners of BARSANA RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BARSANA RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.